THE COST TO RENOVATE
This is Haim Zahavi's estimated construction draw schedule from June 1, 2007 to Sept. 16, 2008. It is based on his ability to perform interior work during this summer and the summer of 2008:

June 1: Theater Interior . . . . . . . . .$200,000
July 2: Theater Interior . . . . . . . . . .$200,000
Aug. 3: Theater Interior . . . . . . . . .$200,000
Sept. 4: Cofferdam . . . . . . . . . . . .$1,000,000
Oct. 5: Foundation . . . . . . . . . . . . .$333,333
Nov. 6: Rough Carpentry . . . . . . .$333,333
Dec. 7: Structural Steel . . . . . . . . .$333,333
Jan. 8: Roof, Windows, Doors . . . .$333,333
Feb. 9: Theater Finish . . . . . . . . . . .$333,333
March 10: Restaurant/Residential .$333,333
April 11: Rough Utilities . . . . . . . .$333,333
May 12: Life Safety/Theater C.O .$333,333
June 13: Restaurant/Residential . . .$333,333
July 14: Finishes/Elevator . . . . . . .$333,333
Aug. 15: Finishes/Elevator . . . . . . .$333,333
Sept. 16: Proposed Completion . . .$333,333
Total reconstruction cost . . .$5,600,000